New England, New South Wales.
Where the New England tablelands sit, what the climate and rainfall do, what is farmed there, and the transmission, generation and storage being planned.
Rocky Creek, InfraAg's first property, is in the New England region of New South Wales. This is a short profile of the region from public sources.
Where is New England?
New England is the high country of northern New South Wales, on the Northern Tablelands of the Great Dividing Range. Its main centre is Armidale, with Glen Innes, Inverell and Tenterfield to the north and Tamworth at the southern edge, where the tablelands fall away to the slopes.
The NSW Government's Northern Tablelands Local Land Services region covers about 40,000 square kilometres across six local government areas: Tenterfield, Glen Innes-Severn, Inverell, Armidale, Uralla and Walcha. It describes the area as the largest highland region in Australia, with an average elevation above 1,000 metres. The land runs from 257 metres at Yetman in the north-west to 1,536 metres at Round Mountain near Ebor.
In state planning, New England is paired with the North West as a single region of twelve local government areas, home to around 186,000 people in 2021. Tamworth and Armidale are its two busiest centres.
What is the climate like?
The tablelands have a temperate climate with warm summers and cool winters, and they are the wettest part of northern inland New South Wales. Average annual rainfall is 1,200 to 1,600 millimetres along parts of the New England Tablelands, falling to 400 to 800 millimetres on the slopes and plains to the west.
More rain falls in summer than in any other season, and the rest of the year is fairly even. Winter is the driest season. Year-to-year variability is considerable, and the region's rainfall is shaped by the Great Dividing Range and by larger patterns such as the El Niño Southern Oscillation.
Altitude sets the temperature. Along the higher parts of the tablelands, summer average maximums are around 20 degrees, winter average minimums sit between minus 2 and zero, and there are typically 90 to 110 nights a year below 2 degrees.
What is farmed there?
New England is grazing country. Beef cattle, sheep and wool are the main industries on the tablelands, and the NSW Government lists forestry, apples and stone fruit, potatoes, glasshouse tomatoes, dairy, alpacas and cool-climate wine as smaller ones.
Cattle and sheep graze the cooler tablelands around Walcha, Armidale and Glen Innes. Further west, on the slopes and plains around Moree, Narrabri and the Liverpool Plains, the land turns to grain and cotton. Together, the New England North West region produces about a fifth of the state's agricultural output.
What the tablelands give a grazier is summer-dominant rainfall at an altitude that keeps the heat off. The trade-off is a cold winter, a winter feed gap, and the need to carry stock through dry years.
What energy infrastructure is being built?
New transmission is being planned into the tablelands, with generation and storage expected to connect around it. The NSW Government's energy infrastructure agency, EnergyCo, is the planner for a project that would build new transmission lines and energy hubs to link the region to the existing network at Muswellbrook in the Hunter.
The backbone is a pair of new 500 kilovolt transmission lines from Bayswater Power Station near Muswellbrook north into the tablelands. The proposed alignment runs between Bayswater and Boorolong over approximately 305 kilometres, through the Muswellbrook, Upper Hunter, Singleton, Tamworth, Walcha, Uralla and Armidale local government areas. Energy hubs, which EnergyCo describes as a modern type of substation, collect power from solar, wind and storage projects and feed it into the lines.
The project is being assessed as critical State significant infrastructure. Its environmental impact statement was released on 15 October 2026 and is on public exhibition until 26 November 2026. EnergyCo is running a competitive process to appoint a network operator to design, build, finance, operate and maintain the lines, with a preferred operator expected by late 2027 and construction to follow financial close in 2028. The initial network capacity is 6 gigawatts, delivered in two stages.
The planning designation behind the work is the New England Renewable Energy Zone, gazetted by the NSW Government on 17 December 2021 under the Electricity Infrastructure Investment Act 2020 and amended in October 2026; EnergyCo's formal name for the transmission works is the New England REZ Network Infrastructure Project. Solar, wind, battery and pumped hydro projects are expected to connect to the hubs, though which ones will not be known for several years. An access scheme for the zone was declared on 23 October 2026.
What does this mean for land in the region?
It means land on the tablelands will increasingly be asked to do two jobs: feed people and carry power. A property that is sound grazing country and also sits near new transmission is in a position few properties share.
The farming does not change because of the lines. Beef, sheep and wool remain the base, the climate remains what it is, and the owner's first duty remains the productive capacity of the land. What changes is the set of decisions an owner faces: where a hub, a line or a generation project might fit, which parts of a property should be left alone, and how any proposal sits with neighbours and the district.
That is the work InfraAg has taken on at Rocky Creek, and it is why the region matters to us.
Sources
- NSW Government, Local Land Services, Northern Tablelands regional profile
- NSW Government, Local Land Services, Northern Tablelands
- NSW Department of Planning, Housing and Infrastructure, New England North West Regional Plan 2041
- NSW Government, AdaptNSW, New England and North West
- NSW Government, New England North West climate change snapshot
- EnergyCo, New England REZ Network Infrastructure Project
- EnergyCo, New England Renewable Energy Zone
- EnergyCo, Frequently asked questions
- EnergyCo, Renewable energy generation projects in the New England Renewable Energy Zone
- EnergyCo, Network operator