Reading the Integrated System Plan: what it means for regional land

Every two years the Australian Energy Market Operator publishes a document that shapes where Australia's electricity infrastructure will be built for the next quarter century. The Integrated System Plan is long, technical and written for engineers, regulators and investors. It is also the single most useful public document for anyone who owns land in a region the grid is moving into. This guide explains what it is, how it is made, what the 2026 edition says, how to read its maps, and what it does and does not mean for a landowner.

What is the Integrated System Plan?

The Integrated System Plan (ISP) is AEMO's roadmap for the power system that serves the National Electricity Market over at least the next twenty years. Its central output is an optimal development path: the mix of generation, storage and network investment that meets consumer needs and government energy policies at least cost through to 2050.

AEMO describes the ISP as assessing the options available and identifying the lowest-cost, resilient and pragmatic path to the market's energy future, which governments and industry then use to progress investment and inform policy. The National Electricity Market covers Queensland, New South Wales, the ACT, Victoria, South Australia and Tasmania. Western Australia and the Northern Territory run separate systems and are outside the plan.

Two things make the ISP different from an ordinary report. First, it has legal standing. Under the National Electricity Rules, the ISP "actions" key transmission projects by triggering the regulatory investment test that transmission businesses must run before major investments, and the Australian Energy Regulator sets binding guidelines on cost-benefit analysis and on best practice in demand modelling that AEMO must follow. Second, it is whole-of-system. It looks at generation, storage, transmission, distribution, gas supply and consumer equipment together, rather than one project at a time.

Who publishes it, and how often?

AEMO publishes the ISP every two years, with the current edition released on 25 June 2026 and the next, the 2028 ISP, already in development.

The sequence so far is the 2018, 2020, 2022, 2024 and 2026 plans. Each one revises the last, sometimes substantially. The 2026 plan, for instance, reduced the amount of new transmission needed compared with the 2024 edition because more storage and better siting lowered the requirement. Anyone reading an ISP should assume the next one will move again.

The plan is not produced alone. The AER reviews each draft and the inputs behind it. An ISP Consumer Panel brings a consumer perspective. Transmission businesses, generators, state governments and community groups make submissions at every stage. The 2026 ISP page lists a consultation summary report and non-confidential submissions alongside the plan itself.

How is the plan put together?

Each ISP is built in a published sequence that runs for roughly two years, and every step is open to consultation. Understanding the sequence tells a reader how firm any given statement in the plan is.

  1. Inputs, Assumptions and Scenarios Report (IASR). AEMO sets out the scenarios it will model and the inputs behind them: demand, technology costs, fuel prices, policy settings, build limits. The 2025 IASR was published on 31 July 2025 after consultation, with an addendum on 10 December 2025.
  2. ISP Methodology. A separate document describes the modelling approach. The current methodology was updated in June 2025 to complete a four-yearly review and to incorporate Energy Ministers' response to a review of the ISP.
  3. Supporting reports. An Electricity Network Options Report lists the transmission and distribution options available to the model, and a Gas Infrastructure Options Report does the same for gas. A transmission cost database sets the unit costs.
  4. Scenario weighting. Before the draft, AEMO assesses how likely each scenario is. For the 2026 plan it ran a full-day workshop with 25 energy sector representatives in September 2025, who voted on 18 key parameters underlying the scenarios.
  5. Draft ISP. Published for consultation; the Draft 2026 ISP appeared on 10 December 2025.
  6. Final ISP. Published with appendices, data files and GIS boundaries; the 2026 ISP on 25 June 2026.

The 2026 ISP's appendices cover stakeholder engagement, development opportunities, renewable energy zones, system operability, network investments, cost-benefit analysis, system security, social licence, demand side factors and gas development projections. The demand side factors statement responds to a December 2024 rule change by the Australian Energy Market Commission requiring AEMO to consider demand side resources more fully.

What are the scenarios?

The ISP models several scenarios because the future is uncertain, and then tests candidate development paths against all of them. The 2026 ISP used three: Step Change, Slower Growth and Accelerated Transition.

Step Change is AEMO's central case and was identified as the most likely scenario in the 2026 scenario weighting. Reporting on the final plan put its weighting at 46%. Slower Growth, previously called Progressive Change, assumes a slower pace of electrification and investment. Accelerated Transition assumes a faster one. AEMO also runs sensitivities, including high growth and constrained delivery, to test whether the plan holds up if things go better or worse than expected.

The scenarios matter to a landowner because they are the source of the range in any ISP figure. When the plan says a region may need a certain amount of generation, the number differs by scenario, and the maps often show different build-outs for each. A reader who sees only the Step Change map sees the central case, not the range.

Scenario Pace of change Role in the 2026 ISP
Step Change Central; steady electrification and policy delivery Most likely scenario; the optimal development path is anchored on it
Slower Growth Slower demand growth and investment Tests the plan against a slower world
Accelerated Transition Faster electrification and build Tests the plan against a faster world
Sensitivities (high growth, constrained delivery) Variations on Step Change Check that the destination holds if delivery is delayed or demand surges

What is the optimal development path?

The optimal development path (ODP) is the set of investments that delivers the lowest cost across the scenarios, weighted by their likelihood, while meeting reliability, security and policy requirements. It is the ISP's answer, and the projects on it carry regulatory consequences.

AEMO builds candidate development paths from the options in its network and gas reports, models each against every scenario, and selects the path with the highest net market benefit. The AER's cost-benefit analysis guidelines govern how that is done. Projects on the ODP are classed as actionable, future or anticipated. An actionable ISP project is one AEMO says should proceed now; it triggers the regulatory investment test for transmission, in which the transmission business must adopt the need identified in the ISP and consult on options. Future projects are expected later and are reassessed in each plan. Anticipated projects are already under way.

The 2026 ISP's ODP, as reported by Energy Networks Australia and specialist press, includes about 6,000 kilometres of new transmission, roughly 120 gigawatts of utility-scale wind and solar, almost 50 gigawatts of utility-scale storage and hydro, and 17 gigawatts of flexible gas generation by 2050. Reporting puts the total investment at about $106 billion, of which about $6 billion is transmission, and the net market benefit of the plan at $28 billion. Under the ODP, renewables would supply 82% of electricity nationally by 2030 and 98% by 2050, with most of the remaining coal fleet withdrawn by 2038 and all of it by 2049.

Two features of the 2026 ODP matter for land. Consumer energy resources, meaning rooftop solar and home batteries, are treated as part of the system, and AEMO estimates that coordinating about half of them could avoid several billion dollars of grid-scale storage. And distribution network spending appears in the plan for the first time, to free up capacity for mid-scale generation and storage closer to where power is used.

What does it say about transmission and where generation goes?

The ISP's core geographic statement is that the best wind and solar are not where the coal stations are, so the network must extend into new regions and the generation will follow the resource and the network. The 2026 plan calls for about 6,000 kilometres of new transmission to be added to the existing 44,000 kilometre network, an extension of roughly one-seventh, with about 3,500 kilometres of that already committed, anticipated or in progress.

That figure is down from close to 10,000 kilometres in earlier plans. The reason given is that more storage, including a large volume of batteries already in the connection process, reduces the need for long lines. Reporting on the plan notes that about 40% of the new transmission strengthens interstate links and about 60% connects new capacity within states. Around 20 transmission projects are actionable or under way. AEMO's accompanying release states that $6 billion of transmission investment to 2050 would avoid nearly $30 billion in capital, operating and fuel costs compared with a system built without it.

On generation, the plan expects utility-scale wind and solar to grow roughly fivefold from about 23 gigawatts today. Reporting on the plan notes that about 67 gigawatts of projects were in AEMO's connections process, 45 gigawatts of them grid-scale batteries, well ahead of what the ODP needs by 2030. Demand underpins all of this: AEMO's central scenario has underlying consumption rising from about 205 terawatt hours a year to about 390 by 2050, with household draw from the grid falling as rooftop solar grows and business and industrial demand roughly doubling.

The ISP identifies renewable energy zones as areas where generation can be grouped and connected efficiently, and provides indicative boundaries for them. Those boundaries are planning constructs, and a good deal of generation and almost all transmission sits outside them. State governments decide which zones are declared and how they are developed; in New South Wales that work sits with EnergyCo, which leads delivery of the state's priority transmission projects and manages land and easement acquisition for them. The 2026 ISP page also carries a ministerial letter about the New England network infrastructure project in New South Wales, an example of how state decisions enter the plan.

How do you read its maps?

The ISP's maps show candidate locations and corridors, not sites and routes, and they are drawn for the system as a whole rather than for any property. Reading them well means knowing what each element represents and how firm it is.

Sub-regions. The ISP divides the market into sub-regions that are larger than renewable energy zones and smaller than states. Most of the plan's build figures are reported by sub-region. AEMO publishes the indicative sub-regional boundaries as GIS data with the 2026 ISP.

Indicative zone boundaries. The plan shows renewable energy zones as shaded areas with indicative boundaries, also published as GIS data. They mark where the model has placed generation, not where it will go. State declarations, where they exist, are the ones that carry planning effect.

Transmission lines. Existing lines are shown as the base network. New projects appear as lines between sub-regions or zones, drawn schematically. A line on the ISP map joins two points; the corridor and route are determined later by the transmission business through the regulatory investment test, environmental assessment and landholder negotiation. Line colour or style usually distinguishes actionable, future and anticipated projects, and the legend on each map should be checked rather than assumed.

Generation and storage. Build quantities appear as figures or bars by sub-region and by scenario, rather than as dots on the map. The generation and storage outlook workbook, published with the plan, holds the underlying numbers.

Timing. Every project and build figure carries an expected timing, by scenario, and timing has moved in every edition to date.

A practical method: find the sub-region, note what the plan expects to be built there and when under Step Change, check whether any actionable or future transmission project touches it, then compare the other scenarios to see how much that picture changes. If a property lies near an indicative line, the next documents to read are the transmission business's planning reports and the state planning body's project pages, because those are where lines become routes.

What does the ISP mean for a landowner?

The ISP tells a landowner the direction the system is moving and roughly when a region is expected to be needed, and nothing more specific than that. It is a plan for the system, not a decision about any parcel of land.

The ISP does The ISP does not
Identify which regions the system expects to draw on, and in what order Approve, consent to or fund any particular project
Trigger the regulatory process for actionable transmission projects Choose the route of a line or the site of a substation
Publish the scenarios, timing and quantities behind its expectations Bind a landowner, create an easement or require access
Provide indicative zone and sub-region boundaries as data Guarantee that a project shown will be built, or built on time
Explain why storage, demand and policy change the plan Tell an owner what a lease, option or easement should be worth

Three implications follow. First, proximity to an indicative line or a zone boundary is a signal of likely activity, not a right or a promise, and it may disappear in the next edition. Second, the processes that actually affect a property, namely the regulatory investment test, state planning approval, environmental assessment and negotiation of options, leases and easements, come after the ISP and have their own public steps and timelines. Third, because the plan is revised every two years and the technology mix keeps shifting, the land that stays useful is land that suits several possible outcomes rather than one.

What should you read alongside it?

The ISP is the top of a stack of planning documents, and the ones below it get closer to the ground. For a landowner the most useful are the transmission businesses' annual planning reports, state planning bodies' project pages, and the planning guidelines that govern how projects are assessed.

Transmission businesses publish annual planning reports describing their networks and proposed projects, and run the regulatory investment test consultations for each actionable ISP project; AEMO's 2026 ISP page lists three newly actionable projects for which it sought non-network options by 17 September 2026. In New South Wales, EnergyCo publishes project material for the transmission it is delivering, including how it acquires land and easements and compensates affected landholders. The NSW Department of Planning's Renewable Energy Planning Framework sets out the guidelines for wind, solar and transmission projects, including a transmission guideline, benefit-sharing guidance and advice for landowners on private agreements. Other states have their own equivalents.

How does InfraAg use it?

We read each ISP for direction and for change, not for prediction. The plan tells us which regions the system expects to need and how that expectation is shifting between editions; it does not tell us what to buy. We buy land on its agricultural merit, in regions the plan and the state documents suggest will stay relevant whichever scenario unfolds, and we try to own country that could suit more than one use. The ISP is the best public map of where the grid is going. The farm still has to stand on its own.